We are building a house West of the Ashley in a sub called Carolina Park. Below are pictures of the different phases.
Day One- Closed on Lot 302.
Underground plumbing and form work for foundation
Foundation
The framing has begun..............
Framing almost done......
House is wraped and singles on the roof
Ready for pre-drywall inspection
The house is 2 months into the 4 months and is right on schedule. All of the plumbing, HVAC, and electrical is in. Next step is the drywall and siding. We go by 2-3 times a week and it very exciting to fallow the house building process.